  1. I had to do a double take on thursday when I saw a crane take away the booth from the parking lot across the street from the future Omni. Didn't think much of it until Friday when I saw that it was closed off. Even the Hyatt bus was parked off to the side (blocking a sidewalk, I must add).

    Anyone know about what's going on? DTG? Is this connected to the Omni or has something ELSE slipped uner the radar?

    The current plan is to close the sidewalk on Polk and one lane of traffic to install a dual cab exterior hoist. We are expecting to have this hoist in place for 6-9 months until we get the interior elevators running. Anticipated start date is Jan-Feb 07.

    Also the existing garage will be closed to the public once construction starts.

  2. Several. I am not positive, but I think it was up during the Super Bowl, which would make it going on 4 years.

    EDIT: Holy Cow! How about 6 YEARS! According to this blog, the scaffolding went up after Tropical Storm Allison, which caused some of the panels to come loose. Allison was in June 2001!

    http://politicalblog.abc13.com/2007/07/index.html

    The scaffolding has been up for about 4 years. (I know this because I'm involved with the project. The project is scheduled to be completed by June 08.

  3. They have actually been doing work on the Chronicle building during the last month or so.

    They are currently removing all the marble from the building. Aluminum panels will be installed from the 2nd floor to the roof. The ground floor will have new stone along with a new plaza. The existing parapet is also being removing. Once construction is complete in July 08 the building will have a nice new look.

  4. Just to clear a couple of things up.

    The group that purchased the building owns the parking garage below the building. Once construction starts the garage will be closed. Currently the Hyatt and individuals lease out parking in the garage.

    As far as the pre-cast falling off the building - Eng. have reviewed and are in the process of reviewing the skin on the building. Some spawling on the pre-cast panels does exist. The owners are working on a plan to mitigate this situation. It just will take a little time.

    The hotel is scheduled to open Sept. 09

×
×
  • Create New...