Noticed the sign on west gray westbound just before Dolce is updated to say "Lane Closures April 4 to May 4" i believe are the dates. So hopefully that is for Dolce, though could be for Proguard working on the sidewalk in front of their location.

Link to comment
Share on other sites

  • 2 weeks later...
  • 3 weeks later...

This is what I understand about the status of the project at this time:

 

West Building:

- Due to heavy rain last year, the top two floors had to be deconstructed and replaced, along with all the siding.

- Nearly all "fixes" are complete, with some small additional work on the roof required.

- Currently waiting on permits to begin substantial work again.

 

East Building:

- Similar issues, but farther along.

- At this time, they are working on permits floor by floor.

- Top floor just received permits for plumbing/electrical and they just started installing that equipment.

- They will work their way down as the permits come through.

Link to comment
Share on other sites

  • 2 weeks later...
  • 1 month later...
  • 2 weeks later...
  • 3 weeks later...
  • 3 weeks later...
  • 3 weeks later...
  • 4 weeks later...
  • 3 weeks later...

Archived

This topic is now archived and is closed to further replies.

×
×
  • Create New...